Going Live

Old PV System moved to Library Roof
Click image to enlarge
During September 2010 the new solar photovoltaic system went into live operation, producing about 13.5% of the Truro Central School's electricity requirements.

Superintendent Brian Davis, along with assistant town administrator Charleen Greenhalgh can be seen "throwing the switch" which connects the new system to the NSTAR grid.

Funding and Contracting

In April 2009 the voters at the Annual Town Meeting approved warrant article #9 and appropriated $70,000 toward the purchase of a new 25,000 watt solar photovoltaic system. The system would be installed on the south-facing roof of the Truro Central School gym. The expectation was that the system would cost more than twice this appropriation, and that the town would endeavor to obtain grant funds to make up the difference.

Bid Cover Page In the summer of 2009, we went out to competitive bid, and the low cost bidder was E2Solar, Inc. from Hyannis, at a bid cost of $113,148. Fortunately, we were then able to obtain a $90,000 grant for our "shovel-ready" project that originated from the federal "stimulus" American Recovery and Reinvestment Act. The grant was awarded through the Energy Efficiency and Conservation Block Grant program administered by the Massachusetts Department of Energy Resources. We also obtained a $4,139 grant from funds under the Massachusetts Renewable Energy Trust's Clean Energy Choice Program. With our town appropriated funds and these grants, we had enough financing to contract for the system to be installed. In the spring of 2010, the Board of Selectmen and Jason Stoots, president of E2Solar, signed a contract for the new PV system.

Installation Process

After obtaing the various permits and approvals, the installation got underway in July. The schedule was tight, because all work had to be completed by the end of August, before the school re-opened and the students returned. But excellent teamwork between E2Solar and school personnel, especially school custodian Fernando Hernandez, kept the project moving crisply along.

Relocating the Existing System

Old PV System moved to Library Roof
Click image to enlarge
The existing 12 panel 2,000 watt system, which was installed several years ago on the gym roof, first had to be moved.
Old PV System moved to Library Roof
Click image to enlarge
A new location for it was found on the south-facing school library roof. By the way, that roof, as it turns out, has room for about 12,000 additional watts of solar panels in the future.

Mounting the new Solar Photovoltaic Panels

Inverters
Click image to enlarge
Weatherproof metal mounting feet, which fasten into to the structural roof, could now be installed covering most of the gym roof. Onto those feet were bolted aluminum rails that would hold the photovoltaic panels themselves. Each panel is carefully bolted to the rails, and then wired to the rest of the array of panels.

Roof Work Complete

Inverters
Click image to enlarge
When all the panels were finally installed, they were then connected to produce DC current. Each Evergreen Solar ES-A-200-fa3 panel is about 3' by 5' and has a capacity of producing 200 watts. There are 124 panels in total.

In order to be used, that DC current must first be converted to AC current and then fed into the school's electrical system.

Connecting the Panels to the Inverters

Inverters
Click image to enlarge
After the DC current is produced by the photovoltaic panels, it travels along the wiring down into the equipment closet. There it is run through 4 Solectria 5300 inverters which convert it to AC current.

That AC current is then fed into the school's electrical subpanel where it can be used to help meet the electrical demands.

Connect to the NSTAR Grid

Inverters
Click image for Net Metering FAQs
The electric panels in the school are already connected to the NSTAR grid, which supplies AC power. On a sunny day when school is not in session, the solar panels' production might exceed the school's demands for electricity, in which case the excess current will flow back to NSTAR. In that case, the electric meter literally runs backwards.
Inverters
Click image to enlarge
In case of power failure on the NSTAR side, their technicians can "throw the switch" to the off position, so that our solar system doesn't feed electricity back to the electric pole outside potentially endangering repair crews.

Financial Payback

In future eNewsletters, we hope to explain in more detail the financial aspects of the new solar installation. It will be an excellent investment for Truro and pay dividends in terms of reduced electricity costs and environmental impact for years to come.